ReNew Energy Global
Listed IPP — per-stock model.
Latest concall
Q4 FY26 · 18 May 2026- Operating portfolio ~12.8 GW (+25% YoY adj.); commissioned record 2.4 GW in FY26
- FY26 adj. EBITDA ₹98.5 bn (+25%, above guidance); PAT ₹10.4 bn (2.3x YoY)
- Q4 FY26 adj. EBITDA ~₹23.7 bn (₹4 bn from manufacturing)
- Leverage improved: interest/EBITDA 61.5% vs 66%; cash flow to equity +45% to ₹21.6 bn
1.6-2.4 GW contracted capacity under construction for FY27; 4 GW solar-cell line to commission by FY27-end.
- FY27 adj. EBITDA guidance ₹103-109 bn; build 1.6-2.4 GW of new capacity
- FY27 cash flow to equity ₹18-22 bn; commission 4 GW cell facility (ALMM-2) by year-end
- Pending non-binding $6.75/share take-private (CPP Investments + CEO Sinha); binding deal targeted Jun-2026
Q4 FY26 earnings call & 6-K (18 May 2026); SEC 13D/A take-private filings (May 2026)
UC + pipeline
Revenue FY26E
EBITDA margin
P/E
Financials
Annual · ₹ crore · E = estimate.
Annual financials
₹ crore · FY25 → FY28E
Revenue, EBITDA & margin
Bars ₹cr (left) · margin % (right)
Quarterly
₹ crore · recent quarters.
Quarterly financials
₹ crore
Revenue & margin trend
Bars ₹cr (left) · margin % (right)
Valuation
As of 31 Mar 2026
P/E
Operating metrics
What the rest of the dashboard tracks for ReNew Energy Global — capacity, auctions, offtake, manufacturing and returns.
Auctions won
From the maintained auction feed
| Date | Agency | Type | MW | ₹/kWh | Source |
|---|---|---|---|---|---|
| 23 Dec 2024 | NTPC | Solar | 300 | 2.55 | source |
Commissioning pipeline
Guided COD tracked from concalls, with slippage vs earlier guidance
| Project | Capacity | Original | Current | Slip | Status |
|---|---|---|---|---|---|
FY25 utility build (solar + wind) Guided 1.9-2.4 GW COD by end-FY25 but only 1.48 GW commissioned; ~600 MW evacuation-dependent slipped, ~466 MW COD'd just after year-end. | 2.15 GW | Q4 FY25 | Q1 FY26 | +1Q | delayed |
FY26 utility build (solar + wind + BESS) | 2.4 GW | Q4 FY26 | Q4 FY26 | — | commissioned |
FY27 utility build | 2 GW | Q4 FY27 | Q4 FY27 | — | on track |
Dholera 4 GW TOPCon cell expansion (Gujarat) | 4 GW | Q3 FY27 | Q3 FY27 | — | on track |
PPA / PSA signings
Power-purchase agreements from the maintained tracker
| Date | Agency | Type | MW | ₹/kWh |
|---|---|---|---|---|
| 23 Dec 2024 | NTPC | Solar | 300 | 2.55 |
Policy exposure
Schemes whose impact note names this company
- ISTS Charge Waiver (Solar/Wind)DemandActive
Losing the waiver raises delivered-power costs for inter-state IPPs — Adani Green, ReNew, Avaada, SJVN — pushing them to commission before the deadline.
- FDRE (Firm & Dispatchable Renewable Energy) TendersStorageActive
Reshapes bidding for large IPPs — Adani Green, ReNew, NTPC, JSW, ACME — rewarding those with solar-plus-wind-plus-storage portfolios; drives the firm-power share seen in the tender mix.
- RPO / RGO TrajectoryDemandActive
Underpins offtake for every IPP — Adani Green, ReNew, NTPC Green, Tata Power, JSW; non-compliant DISCOMs face penalties, which indirectly supports new PPA signings.
Operating & order mix
Unit economics and the order book.
Shareholding
% · as of 31 Mar 2026
Shareholding pattern
%