ReNew Energy Global

Listed IPP — per-stock model.

As of 31 Mar 2026
IPP
CMP 6

Latest concall

Q4 FY26 · 18 May 2026
  • Operating portfolio ~12.8 GW (+25% YoY adj.); commissioned record 2.4 GW in FY26
  • FY26 adj. EBITDA ₹98.5 bn (+25%, above guidance); PAT ₹10.4 bn (2.3x YoY)
  • Q4 FY26 adj. EBITDA ~₹23.7 bn (₹4 bn from manufacturing)
  • Leverage improved: interest/EBITDA 61.5% vs 66%; cash flow to equity +45% to ₹21.6 bn
Order-book execution

1.6-2.4 GW contracted capacity under construction for FY27; 4 GW solar-cell line to commission by FY27-end.

Management guidance
  • FY27 adj. EBITDA guidance ₹103-109 bn; build 1.6-2.4 GW of new capacity
  • FY27 cash flow to equity ₹18-22 bn; commission 4 GW cell facility (ALMM-2) by year-end
  • Pending non-binding $6.75/share take-private (CPP Investments + CEO Sinha); binding deal targeted Jun-2026

Q4 FY26 earnings call & 6-K (18 May 2026); SEC 13D/A take-private filings (May 2026)

UC + pipeline

2.4GW
own capacity, not an order book

Revenue FY26E

15,064₹ cr

EBITDA margin

65.4%

P/E

15.0×

Financials

Annual · ₹ crore · E = estimate.

Annual financials

₹ crore · FY25 → FY28E

PeriodRevenueEBITDAEBITDA %PATGross %ROE %ROCE %CapexNet debtEPS ₹WC days
FY238,9316,20069.4%-503
FY249,6536,92271.7%415
FY2510,9077,91972.6%459
FY2615,0649,85265.4%1,039
Source Nasdaq: RNW (take-private ongoing)· As of 31 Mar 2026

Revenue, EBITDA & margin

Bars ₹cr (left) · margin % (right)

Source Nasdaq: RNW (take-private ongoing)· As of 31 Mar 2026

Quarterly

₹ crore · recent quarters.

Quarterly financials

₹ crore

QuarterRevenueEBITDAEBITDA %PATPAT %
Q1FY264,1182,72266.1%51312.5%
Q2FY263,8562,62468.0%46812.1%
Q3FY263,1372,13868.2%-20-0.6%
Q4FY263,9552,36659.8%782.0%
Source Nasdaq: RNW (take-private ongoing)· As of 31 Mar 2026

Revenue & margin trend

Bars ₹cr (left) · margin % (right)

Source Nasdaq: RNW (take-private ongoing)· As of 31 Mar 2026

Valuation

As of 31 Mar 2026

P/E

15.0×

Operating metrics

What the rest of the dashboard tracks for ReNew Energy Global — capacity, auctions, offtake, manufacturing and returns.

12.6 GW
Operational
3 GW
Under construction
5.4 GW
Pipeline
21 GW
Target FY30
300 MW
Auctions won
1 auction
2.5 GW
Cell nameplate
ALMM-II 1.766 GW
6 GW
Module nameplate
ALMM List-I
4.8 GW
PLI awarded
1 tranche
7.5%
Greenfield IRR · IPP
at its 65.4% margin
300 MW
PPAs signed
1 agreement

Auctions won

From the maintained auction feed

Tenders
DateAgencyTypeMW₹/kWhSource
23 Dec 2024NTPCSolar3002.55source

Commissioning pipeline

Guided COD tracked from concalls, with slippage vs earlier guidance

IPPs
ProjectCapacityOriginalCurrentSlipStatus
FY25 utility build (solar + wind)
Guided 1.9-2.4 GW COD by end-FY25 but only 1.48 GW commissioned; ~600 MW evacuation-dependent slipped, ~466 MW COD'd just after year-end.
2.15 GWQ4 FY25Q1 FY26+1Qdelayed
FY26 utility build (solar + wind + BESS)
2.4 GWQ4 FY26Q4 FY26commissioned
FY27 utility build
2 GWQ4 FY27Q4 FY27on track
Dholera 4 GW TOPCon cell expansion (Gujarat)
4 GWQ3 FY27Q3 FY27on track

PPA / PSA signings

Power-purchase agreements from the maintained tracker

IPPs
DateAgencyTypeMW₹/kWh
23 Dec 2024NTPCSolar3002.55

Policy exposure

Schemes whose impact note names this company

Policy
  • ISTS Charge Waiver (Solar/Wind)DemandActive

    Losing the waiver raises delivered-power costs for inter-state IPPs — Adani Green, ReNew, Avaada, SJVN — pushing them to commission before the deadline.

  • FDRE (Firm & Dispatchable Renewable Energy) TendersStorageActive

    Reshapes bidding for large IPPs — Adani Green, ReNew, NTPC, JSW, ACME — rewarding those with solar-plus-wind-plus-storage portfolios; drives the firm-power share seen in the tender mix.

  • RPO / RGO TrajectoryDemandActive

    Underpins offtake for every IPP — Adani Green, ReNew, NTPC Green, Tata Power, JSW; non-compliant DISCOMs face penalties, which indirectly supports new PPA signings.

Operating & order mix

Unit economics and the order book.

Shareholding

% · as of 31 Mar 2026

Shareholding pattern

%