Orient Green Power
Listed Wind — per-stock model.
As of 21 Aug 2026
Wind—
CMP ₹9NSE: GREENPOWER
Latest concall
Q4 FY26 · 13 May 2026- Operating capacity ~399 MW (392 MW wind + 7 MW solar); +9.9 MW wind added in FY26
- FY26 PAT ₹71.6 cr (+70%); Q4 seasonal net loss ₹16.6 cr on weak March-quarter wind
- 7 MW Tamil Nadu solar commissioned Dec 2025; ~₹16 cr interest refund aided FY26
- PLF: newer turbines ~22% vs ~17% older; repowering targeting >30% PLF
Order-book execution
6.6 MW wind (₹62 cr RenFra contract) targeted for commissioning by 31 Jul 2026; initial repowering underway.
Management guidance
- 1 GW capacity target retained but slowed; ~50 MW addable from internal accruals
- Repower 10 MW old turbines with 6 MW new Suzlon 2.1 MW units; 17.6 MW solar + 9.9 MW wind planned
- Larger expansion needs external equity; multiple financing options under evaluation
Q4 & FY26 earnings call (13 May 2026, T. Shivaraman/J. Kotteswari); company filings
Revenue FY26E
293₹ cr
EBITDA margin
62%
P/E
20.8×
Financials
Annual · ₹ crore · E = estimate.
Annual financials
₹ crore · FY25 → FY28E
Source Market data (mid-2026) + company filings· As of 21 Aug 2026
Revenue, EBITDA & margin
Bars ₹cr (left) · margin % (right)
Source Market data (mid-2026) + company filings· As of 21 Aug 2026
Quarterly
₹ crore · recent quarters.
Quarterly financials
₹ crore
Source Market data (mid-2026) + company filings· As of 21 Aug 2026
Revenue & margin trend
Bars ₹cr (left) · margin % (right)
Source Market data (mid-2026) + company filings· As of 21 Aug 2026
Valuation
As of 21 Aug 2026
P/E
20.8×
EV / EBITDA
9.2×
P/B
1.0×
Operating metrics
What the rest of the dashboard tracks for Orient Green Power — capacity, auctions, offtake, manufacturing and returns.
Commissioning pipeline
Guided COD tracked from concalls, with slippage vs earlier guidance
| Project | Capacity | Original | Current | Slip | Status |
|---|---|---|---|---|---|
First solar plant (17.6 MW) Delayed early on land due-diligence ('big hole in the land'), trimmed 18->17.6 MW; commissioning holds Q1FY27, full output drifts to Q2FY27. | 0.0176 GW | Q4 FY26 | Q1 FY27 | +1Q | delayed |
Devarkulam wind repowering (6.3 MW) First repowering under TN Life-Extension Policy; enabling policy slipped repeatedly through FY26, benefits now only in H2FY27. | 0.0063 GW | Q4 FY26 | Q1 FY27 | +1Q | delayed |
Operating & order mix
Unit economics and the order book.
Shareholding
% · as of 30 Jun 2026
Shareholding pattern
%
Source Market data (mid-2026) + company filings· As of 21 Aug 2026