NHPC

Listed Utility / PSU — per-stock model.

As of 21 Aug 2026
Utility / PSU
CMP 76NSE: NHPC

Latest concall

Q4 FY26 · 18 May 2026
  • Q4 standalone PAT ₹1,460cr (+71%); FY26 PAT ₹3,689cr (+24.6%); revenue ₹11,615cr.
  • Subansiri Lower: 4 of 8 units (1,000 MW) commissioned; +250 MW unit on 8 May 2026.
  • Parbati-II (800 MW) commissioned Apr-2025 lifted FY26 generation.
  • Karnisar 300 MW solar commissioned in FY26 (revenue ₹86.5cr).
Order-book execution

Subansiri Lower's remaining 1,000 MW commissions unit-by-unit through March 2027; broader hydro pipeline is long-gestation.

Management guidance
  • Remaining four Subansiri units (1,000 MW) commission one-by-one till March 2027.
  • Expanding solar/RE alongside hydro; regulated equity grows as projects capitalize.

Q4 FY26 earnings call, May 18 2026

Revenue FY26E

11,615₹ cr

EBITDA margin

45%

P/E

20.2×

Financials

Annual · ₹ crore · E = estimate.

Annual financials

₹ crore · FY25 → FY28E

PeriodRevenueEBITDAEBITDA %PATGross %ROE %ROCE %CapexNet debtEPS ₹WC days
FY158,2215,13462.0%2,7982.3
FY168,3544,78357.0%2,3651.9
FY178,6234,88457.0%3,4803.0
FY187,7554,24855.0%2,7852.5
FY198,9834,98155.0%2,8362.6
FY2010,0084,85649.0%3,3452.9
FY219,6485,27755.0%3,6003.3
FY229,1444,01344.0%3,7743.5
FY2310,6076,18458.0%4,2613.9
FY249,6314,93651.0%4,0003.6
FY2510,3805,42352.0%3,4123.0
FY2611,6155,23645.0%4,2203.8
Source Market data (mid-2026) + company filings· As of 21 Aug 2026

Revenue, EBITDA & margin

Bars ₹cr (left) · margin % (right)

Source Market data (mid-2026) + company filings· As of 21 Aug 2026

Quarterly

₹ crore · recent quarters.

Quarterly financials

₹ crore

QuarterRevenueEBITDAEBITDA %PATPAT %
Q4FY232,02988844.0%74536.7%
Q1FY242,7571,50555.0%1,09539.7%
Q2FY242,9311,76860.0%1,69357.8%
Q3FY242,05675237.0%62330.3%
Q4FY241,8871,15261.0%60532.1%
Q1FY252,6941,60960.0%1,10240.9%
Q2FY253,0521,80559.0%1,06034.7%
Q3FY252,2871,01544.0%33014.4%
Q4FY252,3471,20551.0%92039.2%
Q1FY263,2141,80256.0%1,13135.2%
Q2FY263,3652,02760.0%1,21936.2%
Q3FY262,22121210.0%32114.4%
Q4FY262,81663723.0%1,54955.0%
Source Market data (mid-2026) + company filings· As of 21 Aug 2026

Revenue & margin trend

Bars ₹cr (left) · margin % (right)

Source Market data (mid-2026) + company filings· As of 21 Aug 2026

Valuation

As of 21 Aug 2026

P/E

20.2×

EV / EBITDA

24.7×

P/B

1.9×

Operating metrics

What the rest of the dashboard tracks for NHPC — capacity, auctions, offtake, manufacturing and returns.

Commissioning pipeline

Guided COD tracked from concalls, with slippage vs earlier guidance

IPPs
ProjectCapacityOriginalCurrentSlipStatus
Karnisar 300 MW solar (Bikaner)
0.3 GWQ2 FY26Q3 FY26+1Qcommissioned
N.P. Kunta 100 MW solar (AP)
Guided COD ~June 2026, pushed from the earlier 'within FY2025-26' schedule; unconfirmed as of mid-2026.
0.1 GWQ4 FY26Q1 FY27+1Qdelayed
Khavda 600 MW solar (Gujarat)
0.6 GWQ3 FY27Q3 FY27on track

Policy exposure

Schemes whose impact note names this company

Policy
  • CPSU Scheme Phase-II (Government Producer)ManufacturingActive

    Directs guaranteed orders to state producers — NTPC, SJVN, NHPC, NLC India — and, through the DCR rule, to the domestic module makers supplying them.

Operating & order mix

Unit economics and the order book.

Shareholding

% · as of 31 Mar 2026

Shareholding pattern

%

Source Market data (mid-2026) + company filings· As of 21 Aug 2026