KPI Green Energy
Listed IPP — per-stock model.
As of 21 Aug 2026
IPP—
CMP ₹313NSE: KPIGREEN
Latest concall
Q4 FY26 · 12 May 2026- FY26 rev ₹2,742cr +56%, PAT ₹509cr +57%; Q4 PAT ₹155cr, EBITDA margin ~37%.
- Installed 1.62 GW, work-in-progress 4.64 GW; total portfolio ~6.26 GW.
- Energized 447 MW in Q4; 376 MW Khavda GUVNL IPP hit by evacuation delays.
- Consolidated debt ~₹4,532cr, D/E jumped to 1.49 on debt-funded expansion.
Order-book execution
4.64 GW work-in-progress commissioning in phases across FY27-28, subject to evacuation approvals.
Management guidance
- Reaffirmed 40-50% annual growth target across CPP and IPP segments.
- BESS capacity to be fully operational by FY27; revenue from FY28.
- IPP cash flows to strengthen FY27-28, easing interest burden over time.
KPI Green Q4 FY26 concall, May 12 2026; ScanX, InvestyWise, Whalesbook, SolarQuarter
UC + pipeline
4.64GW
own capacity, not an order book
Revenue FY26E
2,696₹ cr
EBITDA margin
36%
P/E
13.5×
Financials
Annual · ₹ crore · E = estimate.
Annual financials
₹ crore · FY25 → FY28E
Source Market data (mid-2026) + company filings· As of 21 Aug 2026
Revenue, EBITDA & margin
Bars ₹cr (left) · margin % (right)
Source Market data (mid-2026) + company filings· As of 21 Aug 2026
Quarterly
₹ crore · recent quarters.
Quarterly financials
₹ crore
Source Market data (mid-2026) + company filings· As of 21 Aug 2026
Revenue & margin trend
Bars ₹cr (left) · margin % (right)
Source Market data (mid-2026) + company filings· As of 21 Aug 2026
Valuation
As of 21 Aug 2026
P/E
13.5×
EV / EBITDA
11.4×
P/B
2.0×
Operating metrics
What the rest of the dashboard tracks for KPI Green Energy — capacity, auctions, offtake, manufacturing and returns.
1.7%
Greenfield IRR · IPP
at its 36% margin
Commissioning pipeline
Guided COD tracked from concalls, with slippage vs earlier guidance
| Project | Capacity | Original | Current | Slip | Status |
|---|---|---|---|---|---|
GUVNL Khavda 250 MW solar IPP | 0.25 GW | Q3 FY27 | Q3 FY27 | — | on track |
GUVNL 445 MW / 890 MWh BESS | 0.89 GWh | Q4 FY27 | Q4 FY27 | — | on track |
GUVNL Khavda 370 MW hybrid IPP ~6-7 month push-out: the GSECL government substation (GSS)/evacuation infra ran late; GUVNL agreed to extend PPA start, hybrid balance slips into FY28. | 0.37 GW | Q3 FY27 | Q1 FY28 | +2Q | delayed |
GUVNL 150 MW wind IPP | 0.15 GW | Q3 FY28 | Q3 FY28 | — | on track |
Operating & order mix
Unit economics and the order book.
Shareholding
% · as of 31 Mar 2026
Shareholding pattern
%
Source Market data (mid-2026) + company filings· As of 21 Aug 2026